Langage Energy Centre is an 895MW gas fired power project. It is located in England, the UK. The project is currently active. It has been developed in single phase. The project construction commenced in 2008 and subsequently entered into commercial operation in March 2010.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 895 895 Active England, the UK

Description

The project is currently owned by EP Langage with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Oil.

The project cost is $1,084.203m.

Development Status

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The project construction commenced in 2008 and subsequently entered into commercial operation in March 2010.

Contractors Involved

GE Power was selected to render EPC services for the gas fired power project.

GE Power was selected as the turbine supplier for the Gas fired project. The company provided 2 units of GT26 gas turbines, each with 285MW nameplate capacity.

GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of STF30 steam turbine with 325MW nameplate capacity.

GE Power supplied TOPAIR electric generator for the project.

GE Power supplied steam boiler for the project.

GE Power is the O&M contractor for thermal power project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.