The project is developed and owned by Mainstream Energy Solutions.
The hydro reservoir capacity is 15,000 million cubic meter. The total number of penstocks, pipes or long channels that carry water down from the hydroelectric reservoir to the turbines inside the actual power station, are 12 in number. The penstock diameter is 8.55m.
Development Status
The project construction commenced in 1964 and subsequently entered into commercial operation in 1968.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataContractors Involved
Kainji (Phase-1-Kainji Unit no. 9,10) is equipped with The English Electric kaplan turbines. The phase consists of 2 turbines with 80MW nameplate capacity.
Kainji (Phase-2-Kainji Unit no. 12) is equipped with Andritz Hydro kaplan turbine. The phase consists of 1 turbine with 100MW nameplate capacity.
Kainji (Phase-3-Kainji Unit no. 3,5,6) is equipped with Andritz Hydro propeller turbines. The phase consists of 2 turbines with 120MW nameplate capacity.
Kainji (Phase-4-Kainji Unit no. 11) is equipped with Andritz Hydro kaplan turbine. The phase consists of 1 turbine with 100MW nameplate capacity.
Kainji (Phase-5-Kainji Unit no. 7,8) is equipped with GE Renewable Energy kaplan turbines. The phase consists of 2 turbines with 80MW nameplate capacity.
GE Renewable Energy supplied 2 electric generators for the Kainji (Phase-1-Kainji Unit no. 9,10). The generator capacity is 85 MVA.
GE Renewable Energy supplied 2 electric generators for the Kainji (Phase-5-Kainji Unit no. 7,8). The generator capacity is 85 MVA.
About Mainstream Energy Solutions
Mainstream Energy Solutions Ltd. (Mainstream Energy Solutions) is a hydroelectric power generation plant. The Company generates electricity and sells it to distributors. It is headquartered in Abuja, Nigeria.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.