Jagdulla HEP is a 106MW hydro power project. It is planned on Bheri river/basin in Karnali, Nepal. The project is currently in announced stage. It will be developed in single phase. The project construction is likely to commence in 2024 and is expected to enter into commercial operation in 2027.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 106 | – | 106 | Announced | Karnali, Nepal | Jagdulla Hydropower |
---|
Description
The project is being developed and currently owned by Jagdulla Hydropower.
The gross head of the project will be 800m. The penstock length will be 700m. The project is expected to generate 635 GWh of electricity. The project cost is expected to be around $220m.
The hydro power project consists of 3 units of pelton turbines.
Development Status
The project construction is expected to commence from 2024. Subsequent to that it will enter into commercial operation by 2027.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.