Huaneng Shaanxi Weinan Thermal Power Plant is a 700MW coal fired power project. It is located in Shaanxi, China. The project is currently active. It has been developed in multiple phases. The project construction commenced in 2018 and subsequently entered into commercial operation in April 2020.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 700 700 Active Shaanxi, China

Description

The project is currently owned by China Huaneng Group.

It is a steam turbine with cogen power plant.

The project cost is $423.57m.

Development Status

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The project construction commenced in 2018 and subsequently entered into commercial operation in April 2020.

Contractors Involved

SEPCO1 Electric Power Construction was selected to render EPC services for the coal fired power project.

Huaneng Shaanxi Weinan Thermal Power Plant (Huaneng Shaanxi Weinan Thermal Power Plant Unit I) is equipped with Harbin Electric turbine. The phase consists of 1 turbine with 350MW nameplate capacity.

Huaneng Shaanxi Weinan Thermal Power Plant (Huaneng Shaanxi Weinan Thermal Power Plant Unit II) is equipped with Harbin Electric turbine. The phase consists of 1 turbine with 350MW nameplate capacity.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.