Heze Power Plant is a 1,510MW coal fired power project. It is located in Shandong, China. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in May 1991.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 1,510 | 1,510 | – | Active | Shandong, China |
---|
Description
China Energy Investment, CLP Holdings, EDF International and Luneng Group are currently owning the project.
It is a steam turbine power plant that is used for Baseload.
Development Status
The project got commissioned in May 1991.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataContractors Involved
PowerChina Nuclear Engineering was selected to render EPC services for the coal fired power project.
Heze Power Plant (Heze Power Plant Phase II Unit I) is equipped with Shanghai Turbine N300-16.7/537/537 steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.
Heze Power Plant (Heze Power Plant Phase II Unit II) is equipped with Shanghai Turbine N300-16.7/537/537 steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.
Heze Power Plant (Heze Power Plant Phase III Unit I) is equipped with Dongfang Turbine N300-16.7-537/537-8 steam turbine. The phase consists of 1 steam turbine with 330MW nameplate capacity.
Heze Power Plant (Heze Power Plant Phase III Unit II) is equipped with Dongfang Turbine N300-16.7-537/537-8 steam turbine. The phase consists of 1 steam turbine with 330MW nameplate capacity.
Shanghai Electric Group supplied QFSN2-300-2 electric generator for the Heze Power Plant (Heze Power Plant Phase II Unit I).
Shanghai Electric Group supplied QFSN2-300-2 electric generator for the Heze Power Plant (Heze Power Plant Phase II Unit II).
DEC Dongfang Electric Machinery supplied QFSN2-300-2-20B electric generator for the Heze Power Plant (Heze Power Plant Phase III Unit I).
DEC Dongfang Electric Machinery supplied QFSN2-300-2-20B electric generator for the Heze Power Plant (Heze Power Plant Phase III Unit II).
Doosan Babcock supplied steam boiler for the Heze Power Plant (Heze Power Plant Phase II Unit I).
Doosan Babcock supplied steam boiler for the Heze Power Plant (Heze Power Plant Phase II Unit II).
Dongfang Boiler Group supplied steam boiler for the Heze Power Plant (Heze Power Plant Phase III Unit I).
Dongfang Boiler Group supplied steam boiler for the Heze Power Plant (Heze Power Plant Phase III Unit II).
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.