Hell’s Kitchen Geothermal Project is a 1,100MW geothermal power project. It is planned in California, the US. The project is currently in permitting stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in 2023.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Geothermal 1,100 1,100 Permitting California, the US Controlled Thermal Resources (US)

Description

The project is being developed and currently owned by Controlled Thermal Resources (US).

The geothermal plant is of triple flash type.

The project is expected to supply enough clean energy to power 1,000,000 households.

Development Status

Post completion of the construction, the project is expected to get commissioned in 2023.

Power Purchase Agreement

The power generated from the Hell’s Kitchen Geothermal Project will be sold to Imperial Irrigation District under a power purchase agreement. The offtake capacity is expected to be 40MW.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.