Hai Phong Thermal Power Plant is a 1,200MW coal fired power project. It is located in Hai Phong, Vietnam. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in November 2011.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 1,200 1,200 Active Hai Phong, Vietnam

Description

The project is currently owned by Hai Phong Thermal Power Joint Stock.

It is a steam turbine power plant. The fuel is procured from Hon Gai and Cam Pha.

Development Status

The project got commissioned in November 2011.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Contractors Involved

Dongfang Electric and Marubeni were selected to render EPC services for the coal fired power project.

Hai Phong Thermal Power Plant (Hai Phong Thermal Power Phase I Unit I) is equipped with Fuji Electric steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.

Hai Phong Thermal Power Plant (Hai Phong Thermal Power Phase I Unit II) is equipped with Fuji Electric steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.

Hai Phong Thermal Power Plant (Hai Phong Thermal Power Phase II Unit I) is equipped with Fuji Electric steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.

Hai Phong Thermal Power Plant (Hai Phong Thermal Power Phase II Unit II) is equipped with Fuji Electric steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.

Fuji Electric supplied electric generator for the Hai Phong Thermal Power Plant (Hai Phong Thermal Power Phase I Unit I).

Fuji Electric supplied electric generator for the Hai Phong Thermal Power Plant (Hai Phong Thermal Power Phase I Unit II).

Fuji Electric supplied electric generator for the Hai Phong Thermal Power Plant (Hai Phong Thermal Power Phase II Unit I).

Fuji Electric supplied electric generator for the Hai Phong Thermal Power Plant (Hai Phong Thermal Power Phase II Unit II).

Dongfang Electric supplied steam boiler for the Hai Phong Thermal Power Plant (Hai Phong Thermal Power Phase I Unit I).

Dongfang Electric supplied steam boiler for the Hai Phong Thermal Power Plant (Hai Phong Thermal Power Phase I Unit II).

Dongfang Electric supplied steam boiler for the Hai Phong Thermal Power Plant (Hai Phong Thermal Power Phase II Unit I).

Dongfang Electric supplied steam boiler for the Hai Phong Thermal Power Plant (Hai Phong Thermal Power Phase II Unit II).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.