GPPC Pipavav Power Project is a 702.86MW gas fired power project. It is located in Gujarat, India. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in March 2013.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 702.86 702.86 Active Gujarat, India

Description

The project is currently owned by GSPC Pipavav Power with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Gujarat State Petroleum Corporation Ltd..

Development Status

The project got commissioned in March 2013.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Power Purchase Agreement

The power generated from the project is sold to Gujarat Urja Vikas Nigam under a power purchase agreement for a period of 20 years. The contracted capacity is 702MW.

Contractors Involved

Bharat Heavy Electricals was selected to render EPC services for the gas fired power project.

GPPC Pipavav Power Project (GPPC Pipavav Power Project Block I) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 129MW nameplate capacity.

GPPC Pipavav Power Project (GPPC Pipavav Power Project Block I) is equipped with Bharat Heavy Electricals MS9001FA gas turbine. The phase consists of 1 gas turbine with 222.43MW nameplate capacity.

GPPC Pipavav Power Project (GPPC Pipavav Power Project Block II) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 129MW nameplate capacity.

GPPC Pipavav Power Project (GPPC Pipavav Power Project Block II) is equipped with Bharat Heavy Electricals MS9001FA gas turbine. The phase consists of 1 gas turbine with 222.43MW nameplate capacity.

Bharat Heavy Electricals supplied electric generator for the GPPC Pipavav Power Project (GPPC Pipavav Power Project Block I).

Bharat Heavy Electricals supplied electric generator for the GPPC Pipavav Power Project (GPPC Pipavav Power Project Block II).

Bharat Heavy Electricals supplied steam boiler for the GPPC Pipavav Power Project (GPPC Pipavav Power Project Block I).

Bharat Heavy Electricals supplied steam boiler for the GPPC Pipavav Power Project (GPPC Pipavav Power Project Block II).

Sogex Oman is the O&M contractor for thermal power project. The operation and maintenance contract commenced from 2012, for a period of 10 years.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.