Generation equipment contracts in June 2021 saw 111 contracts announced, marking a rise of 6% over the last 12-month average of 105, according to GlobalData’s power industry contracts database.
- Embed this chart
Embed this chart into your website
Copy and paste the code below into your website to display the chart.
The proportion of contracts by category tracked by GlobalData in the month was as follows:
- Supply & Erection: 83 contracts and a 74.8% share
- Repair, Maintenance, Upgrade & Others: 22 contracts and a 19.8% share
- Project Implementation: four contracts and a 3.6% share
- Consulting & Similar Services: two contracts and a 1.8% share.
Europe leads generation equipment activity in June 2021
Comparing contracts activity in generation equipment segment in different regions of the globe, Europe held the top position with 45 contracts and a share of 40.5% during June 2021, followed by Asia-Pacific with 33 contracts and a 29.7% share and North America with 23 contracts and a 20.7% share.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalData- Embed this chart
Embed this chart into your website
Copy and paste the code below into your website to display the chart.
Wind is leading technology for generation equipment contracts in June 2021
Among the technologies, wind accounted for 55 contracts with a 50% share, followed by thermal with 25 contracts and a 22.7% share and solar with 20 contracts and an 18.2% share.
Generation equipment contracts in June 2021: Top issuers by capacity
The top issuers of generation equipment contracts for the month in terms of power capacity involved were:
- Lausitz Energie Bergbau (Germany): 300MW from one contract
- Oil India (India): 30MW from one contract.
Generation equipment contracts in June 2021: Top winners by capacity
The top winners of contracts for the month in terms of power capacity involved were:
- Siemens Energy (Germany): 300MW from one contract
- Wartsila (Finland): 30MW from one contract.
All publicly-announced contracts are included in this analysis drawn from GlobalData’s Power database, which covers power plants, T&D projects, equipment markets, analysis reports, capacity and generation, and tracks tenders and contracts on a real-time basis.