Fairless Combined Cycle Power Station is a 1,338MW gas fired power project. It is located in Pennsylvania, the US. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in May 2004.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 1,338 | 1,338 | – | Active | Pennsylvania, the US |
---|
Description
The project is currently owned by Starwood Energy Group Global with a stake of 100%.
It is a combined cycle gas turbine (ccgt) power plant. The fuel is procured from Willliams/Transco.
The project generated 7,570,296MWh of electricity.
Development Status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe project got commissioned in May 2004.
Contractors Involved
Fairless Combined Cycle Power Station (Fairless Combined Cycle Power Station Block I) is equipped with GE Power 7F.04 gas turbines. The phase consists of 2 gas turbines with 198.9MW nameplate capacity.
Fairless Combined Cycle Power Station (Fairless Combined Cycle Power Station Block I) is equipped with GE Power D11 steam turbine. The phase consists of 1 steam turbine with 271.2MW nameplate capacity.
Fairless Combined Cycle Power Station (Fairless Combined Cycle Power Station Block II) is equipped with GE Power 7F.04 gas turbines. The phase consists of 2 gas turbines with 198.9MW nameplate capacity.
Fairless Combined Cycle Power Station (Fairless Combined Cycle Power Station Block II) is equipped with GE Power D11 steam turbine. The phase consists of 1 steam turbine with 271.2MW nameplate capacity.
GE Power supplied electric generator for the Fairless Combined Cycle Power Station (Fairless Combined Cycle Power Station Block I).
GE Power supplied electric generator for the Fairless Combined Cycle Power Station (Fairless Combined Cycle Power Station Block II).
Siemens Heat Transfer Technology supplied steam boiler for the Fairless Combined Cycle Power Station (Fairless Combined Cycle Power Station Block I).
Siemens Heat Transfer Technology supplied steam boiler for the Fairless Combined Cycle Power Station (Fairless Combined Cycle Power Station Block II).
IHI Power Services is the O&M contractor for thermal power project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.