El Carmen Combined Cycle Power Plant is an 866MW gas fired power project. It is located in Nuevo Leon, Mexico. The project is currently active. It has been developed in single phase. The project construction commenced in 2017 and subsequently entered into commercial operation in September 2019.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 866 866 Active Nuevo Leon, Mexico Iberdrola

Description

The project was developed by Iberdrola and is currently owned by Iberdrola Mexico with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant.

The project cost is $450m.

Development Status

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The project construction commenced in 2017 and subsequently entered into commercial operation in September 2019.

Power Purchase Agreement

The power generated from the project is sold to Comision Federal de Electricidad under a power purchase agreement for a period of 25 years. The contracted capacity is 150MW.

Contractors Involved

Iberdrola Ingenieria y Construccion SAU was selected to render EPC services for the gas fired power project.

Mitsubishi Power was selected as the turbine supplier for the Gas fired project. The company provided 2 units of M501J gas turbines.

Mitsubishi Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of TC4F steam turbine.

Mitsubishi Power supplied electric generator for the project.

Amec Foster Wheeler supplied steam boiler for the project.

Mitsubishi Power is the O&M contractor for thermal power project.

About Iberdrola

Iberdrola SA (Iberdrola) is an energy utility. It constructs, operates and manages power generation plants, transmission and distribution facilities and other assets. The company produces electricity using conventional and renewable energy sources. It also trades electricity and gas in wholesale markets; and retails electricity, gas, and other related products and services. Iberdrola retails energy to residential, commercial, industrial, institutional and other customers. In its transition to a sustainable energy model, the company makes considerable investments in smart grids, renewable energy, large-scale energy storage and digital transformation, Iberdrola operates in Europe, North America, South America and other regions. Iberdrola is headquartered in Bilbao, Vizcaya, Spain.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.