Duisburg Walsum Power Plant Unit 10 is a 790MW coal fired power project. It is located in North Rhine-Westphalia, Germany. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in December 2013.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 790 | 790 | – | Active | North Rhine-Westphalia, Germany |
---|
Description
The project is currently owned by STEAG with a stake of 100%.
It is a Steam Turbine power plant.
The project generated 4,020MWh of electricity. The project cost is $1,026.3m.
Development Status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe project got commissioned in December 2013.
Contractors Involved
Mitsubishi Power Europe was selected to render EPC services for the coal fired power project.
Mitsubishi Power was selected as the turbine supplier for the Coal fired project. The company provided 1 steam turbine with 790MW nameplate capacity.
Mitsubishi Power supplied electric generator for the project.
Mitsubishi Power supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.