Deri – Tepeoren Line is a 380kV overhead line with a length of 11.3km from Deri, Istanbul, Turkey, to Tepeoren, Istanbul, Turkey.
The project, which is currently under construction, is expected to be commissioned in 2021.
Description
Deri – Tepeoren Line is an overhead line that will be operated by Turkiye Elektrik Iletim. The line will carry alternating current (AC) through double circuit cable.
Approximately $19.6m was financed by the authorities to undertake the construction works of the project.
The development of the Deri – Tepeoren Line project has been approved by the Energy Market Regulatory Authority.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataDeri – Tepeoren Line project development status
The construction works on the Deri – Tepeoren Line project were commenced in 2018 and commissioning is expected in 2021.
About Turkiye Elektrik Iletim
Turkiye Elektrik Iletim (Turkiye) is a state owned power transmission company engaged in the business of transmitting electricity through its power plants in Turkey. It operates transmission facilities and carries out the planning of load dispatch and operation services. Turkiye is also a member of CIGRE Turkish National Committee, Turkish National Committee of Word Energy Council, Turkish Electricity Industry Association, Turkish Public Enterprises Association and Turkish Wind Energy Association. Turkiye operates in Turkey. Turkiye is headquartered in Bahcelievler, Turkey.
Methodology
All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.