Centrolite Substation is a 330kV substation located in Centrolite, Odessa, Ukraine.
The Centrolite Substation project’s construction has begun in 2020. The works are expected to be commissioned in 2022.
Description
Centrolite Substation project, which is an upgrade substation, will be operated by NEC Ukrenergo.
The designed voltage level of the substation is 330/220kV and the operating voltage level is 330/220kV.
The step-in voltage of the project is 330kV and the step-out voltage is 220kV. Upon completion, the substation will have a capacity of 400MVA.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataCentrolite Substation project development status
The project is expected to be commissioned in 2022. Approximately $65.11m was financed by the authorities to undertake the construction works of the project.
About NEC Ukrenergo
NEC Ukrenergo (NEC) is an energy utility service provider that provides electricity transmission. The company’s services include electrical grid networks, capital construction and purchases, dispatch management, power and electricity transmission and distribution services. It develops generating capacity UES Ukraine, Prospects main power grids and investments projects. NEC also provides occupational health, training, environmental issue, personnel policy, and quality management system solutions. The company operates power systems that directly operate inter-state transmission lines and hosts separated entities such as Main data-processing center and Energetik public catering.
Methodology
All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.