Cascavel Oeste – Segredo Line is a 525kV overhead line with a length of 186.4km from Cascavel Oeste, Parana, Brazil, to Segredo, Rio Grande do Sul, Brazil.
The project is expected to be commissioned in 2026.
Description
Cascavel Oeste – Segredo Line is an overhead line that will be operated by Operador Nacional do Sistema Eletrico. The line will carry alternating current (AC) through single circuit cable.
Cascavel Oeste – Segredo Line project development status
The construction works on the Cascavel Oeste – Segredo Line project will be commenced in 2024 and commissioning is expected in 2026.

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataAbout Operador Nacional do Sistema Eletrico
Operador Nacional do Sistema Eletrico (ONS) is a non-profit civil association. The company is engaged in coordinating and monitoring of transmission, generation and distribution of electric power in National Interconnected System (NIS). It perform its operation under the supervision and regulation of the Electric Energy National Agency (ANEEL). ONS is headquartered in Brazil.
Methodology
All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.