Benghazi Combined Cycle Power Plant is a 750MW gas fired power project. It is located in Benghazi, Libya. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 2010.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 750 | 750 | – | Active | Benghazi, Libya |
---|
Description
The project is currently owned by General Electricity Company Of Libya with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Baseload.
Development Status
The project got commissioned in 2010.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataContractors Involved
ACESCo, Daewoo Engineering & Construction and Hyundai Engineering were selected to render EPC services for the gas fired power project.
The Gas fired project have been supplied by Fuji Electric and Siemens.
Siemens supplied V94.3A electric generator for the project.
The steam boilers for the gas fired power project have been supplied byAmec Foster Wheeler and Fuji Electric.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.