Barney Davis Energy Center is a 730.2MW gas fired power project. It is located in Texas, the US. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in July 1976.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 730.2 | 730.2 | – | Active | Texas, the US |
---|
Description
The project is currently owned by Talen Energy Supply with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from ONYX GAS MARKETING CO.
The project generated 1,633,953MWh of electricity.
Development Status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe project got commissioned in July 1976.
Contractors Involved
Barney Davis Energy Center (Barney Davis Energy Center Unit I) is equipped with Siemens Energy steam turbine. The phase consists of 1 steam turbine with 351MW nameplate capacity.
Barney Davis Energy Center (Barney Davis Energy Center Unit II) is equipped with GE Power 7F.04 gas turbine. The phase consists of 1 gas turbine with 189.6MW nameplate capacity.
Barney Davis Energy Center (Barney Davis Energy Center Unit III) is equipped with GE Power 7F.04 gas turbine. The phase consists of 1 gas turbine with 189.6MW nameplate capacity.
Nooter/Eriksen supplied steam boiler for the Barney Davis Energy Center (Barney Davis Energy Center Unit II).
Nooter/Eriksen supplied steam boiler for the Barney Davis Energy Center (Barney Davis Energy Center Unit III).
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.