Yusufeli Dam & HEPP is a 558MW hydro power project. It is located on Coruh river/basin in Artvin, Turkey. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2013 and subsequently entered into commercial operation in 2022. Buy the profile here.
Description
The project is developed and owned by Limak Holding.
The hydro reservoir capacity is 2,200 million cubic meter. The gross head of the project is 191m. The project generated 1,900 GWh of electricity.
Development status
The project construction commenced in 2013 and subsequently entered into commercial operation in 2022.
Contractors involved
Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 3 units of francis turbines, each with 186MW nameplate capacity.
Andritz Hydro supplied electric generator(s) for the project. The generator capacity is 203 MVA.
For more details on Yusufeli Dam & HEPP, buy the profile here.
About Limak Holding
Limak Holding Inc (Limak) specializes in construction, energy, cement, and tourism services. The company is headquartered in Turkey.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.