Wawa is a 500MW hydro power project. It is planned on Wawa,Montalban river/basin in Calabarzon, Philippines. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in a single phase. The project construction is likely to commence in 2029 and is expected to enter into commercial operation in 2032. Buy the profile here.
Description
The project is being developed by Olympia Violago Water & Power. San Lorenzo Ruiz Builders & Developers Group and Vena Energy are currently owning the project.
Wawa is a pumped storage project. The hydro reservoir capacity is planned to be 6.2 million cubic meter.
The hydro power project consists of 3 turbines, each with 167MW nameplate capacity.
Development status
The project construction is expected to commence from 2029. Subsequent to that it will enter into commercial operation by 2032.
Contractors involved
Power Construction Corporation of China is expected to render engineering procurement construction services for the hydro power project.
For more details on Wawa, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.