Wansley Combined Cycle Power Plant is a 1,239MW gas fired power project. It is located in Georgia, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in June 2002. Buy the profile here.
Description
The project is currently owned by Southern Power with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Transco pipeline.
The project generated 5,543,216MWh of electricity.
Development status
The project got commissioned in June 2002.
Contractors involved
KBR was selected to render engineering procurement construction services for the gas fired power project.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 4 units of 7F.04 gas turbines, each with 203.1MW nameplate capacity.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 2 units of D11 steam turbines, each with 213.3MW nameplate capacity.
GE Power supplied electric generator for the project.
GE Power supplied electric generator for the project.
Vogt-NEM supplied steam boiler for the project.
Vogt-NEM supplied steam boiler for the project.
For more details on Wansley Combined Cycle Power Plant, buy the profile here.