Vasilikos Power Plant Phase III & IV is a 440MW dual-fuel fired power project. It is located in Larnaca, Cyprus. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in November 2009. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Vasilikos Power Plant Phase III & IV

Buy the Profile

Data Insights

The gold standard of business intelligence.

Find out more

Description

The project is developed and owned by Electricity Authority of Cyprus.

It is a Combined Cycle Gas Turbine (CCGT) power plant.

Development status

The project got commissioned in November 2009.

Contractors involved

Avax was selected to render engineering procurement construction services for the Vasilikos Power Plant Phase III & IV (Vasilikos Power Plant Phase III & IV Unit I) project. Avax was selected to render engineering procurement construction services for the Vasilikos Power Plant Phase III & IV (Vasilikos Power Plant Phase III & IV Unit II) project. Hitachi Power Europe was selected to render engineering procurement construction services for the Vasilikos Power Plant Phase III & IV (Vasilikos Power Plant Phase III & IV Unit I) project. Hitachi Power Europe was selected to render engineering procurement construction services for the Vasilikos Power Plant Phase III & IV (Vasilikos Power Plant Phase III & IV Unit II) project. Itochu was selected to render engineering procurement construction services for the Vasilikos Power Plant Phase III & IV (Vasilikos Power Plant Phase III & IV Unit I) project.

Vasilikos Power Plant Phase III & IV (Vasilikos Power Plant Phase III & IV Unit I) is equipped with GE Power steam turbine. The phase consists of 1 steam turbine with 70MW nameplate capacity.

Vasilikos Power Plant Phase III & IV (Vasilikos Power Plant Phase III & IV Unit I) is equipped with GE Power 6F.03 gas turbines. The phase consists of 2 gas turbines with 75MW nameplate capacity.

Vasilikos Power Plant Phase III & IV (Vasilikos Power Plant Phase III & IV Unit II) is equipped with GE Power steam turbine. The Dual-Fuel fired phase consists 1 steam turbine.

Vasilikos Power Plant Phase III & IV (Vasilikos Power Plant Phase III & IV Unit II) is equipped with GE Power 6F.03 gas turbines. The phase consists of 2 gas turbines.

GE Power supplied electric generator for the project.

Siemens Heat Transfer Technology supplied steam boiler for the Vasilikos Power Plant Phase III & IV (Vasilikos Power Plant Phase III & IV Unit I).

Siemens Heat Transfer Technology supplied steam boiler for the Vasilikos Power Plant Phase III & IV (Vasilikos Power Plant Phase III & IV Unit II).

General Electric International is the O&M contractor for the Vasilikos Power Plant Phase III & IV (Vasilikos Power Plant Phase III & IV Unit II).

For more details on Vasilikos Power Plant Phase III & IV, buy the profile here.

About Electricity Authority of Cyprus

The Electricity Authority of Cyprus (EAC) is an energy utility, which generates, transmits, distributes and supplies electricity. It owns and operates Moni (open cycle gas turbines), Dhekelia (steam units and internal combustion units), and Vasilikos (steam units, combined cycle units and gas turbine units) power stations. It also develops and manages the national transmission and distribution network. The transmission network connects power stations to load centers. The authority supplies energy to industrial, public lighting and commercial. It also provides customer services such as meter readings, a complaint about street lighting and others. EAC is headquartered in Lefkosia, Nicosia, Cyprus.

This content was updated on 14 October 2024

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.