Upper Trishuli 3A is a 60MW hydro power project. It is located on Trishuli river/basin in Bagmati, Nepal. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2011 and subsequently entered into commercial operation in 2019. Buy the profile here.
Description
The project was developed by Trishuli Jal Vidhyut and is currently owned by Nepal Electricity Authority with a stake of 30%.
Upper Trishuli 3A is a run-of-river project. The gross head of the project is 144.5m. The project generated 489.76 GWh of electricity.
The hydro power project consists of 2 turbines, each with 30MW nameplate capacity.
Development status
The project construction commenced in 2011 and subsequently entered into commercial operation in 2019.
Contractors involved
China Gezhouba Group was selected to render engineering procurement construction services for the hydro power project.
For more details on Upper Trishuli 3A, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.