TH Wharton CCGT Plant is a 664MW gas fired power project. It is located in Texas, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in July 1972. Buy the profile here.
Description
The project is currently owned by NRG Energy with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Kinder Morgan.
Development status
The project got commissioned in July 1972.
Contractors involved
TH Wharton CCGT Plant (TH Wharton CCGT Plant Block I Unit II) is equipped with GE Power Frame 7B/E gas turbine. The phase consists of 1 gas turbine with 57MW nameplate capacity.
TH Wharton CCGT Plant (TH Wharton CCGT Plant Block I Unit IV) is equipped with GE Power Frame 7B/E gas turbine. The phase consists of 1 gas turbine with 57MW nameplate capacity.
TH Wharton CCGT Plant (TH Wharton CCGT Plant Block I Unit I) is equipped with GE Power Frame 7B/E gas turbine. The phase consists of 1 gas turbine with 57MW nameplate capacity.
TH Wharton CCGT Plant (TH Wharton CCGT Plant Block I Unit III) is equipped with GE Power Frame 7B/E gas turbine. The phase consists of 1 gas turbine with 57MW nameplate capacity.
TH Wharton CCGT Plant (TH Wharton CCGT Plant Block I Unit V) is equipped with GE Power steam turbine. The phase consists of 1 steam turbine with 104MW nameplate capacity.
TH Wharton CCGT Plant (TH Wharton CCGT Plant Block II Unit I) is equipped with GE Power Frame 7B/E gas turbine. The phase consists of 1 gas turbine with 57MW nameplate capacity.
TH Wharton CCGT Plant (TH Wharton CCGT Plant Block II Unit II) is equipped with GE Power Frame 7B/E gas turbine. The phase consists of 1 gas turbine with 57MW nameplate capacity.
TH Wharton CCGT Plant (TH Wharton CCGT Plant Block II Unit III) is equipped with GE Power Frame 7B/E gas turbine. The phase consists of 1 gas turbine with 57MW nameplate capacity.
TH Wharton CCGT Plant (TH Wharton CCGT Plant Block II Unit IV) is equipped with GE Power Frame 7B/E gas turbine. The phase consists of 1 gas turbine with 57MW nameplate capacity.
TH Wharton CCGT Plant (TH Wharton CCGT Plant Block II Unit V) is equipped with GE Power steam turbine. The phase consists of 1 steam turbine with 104MW nameplate capacity.
GE Power supplied electric generator for the project.
GE Power supplied steam boiler for the project.
For more details on TH Wharton CCGT Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.