Sagae is a 75MW hydro power project. It is located on Sagae river/basin in Yamagata, Japan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1972 and subsequently entered into commercial operation in 1990. Buy the profile here.
Description
The project is currently owned by Tohoku Electric Power with a stake of 100%.
Sagae is a reservoir based project. The hydro reservoir capacity is 109 million cubic meter. The net head of the project is 117.75m. The project generated 242.854 GWh of electricity.
The hydro power project consists of 1 turbine with 77MW nameplate capacity.
The project has 1 electric generator installed at the site. The generator capacity is 83.4 MVA.
Development status
The project construction commenced in 1972 and subsequently entered into commercial operation in 1990.
For more details on Sagae, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.