Rattlesnake Flat Wind Farm is a 160MW onshore wind power project. It is located in Washington, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2020 and subsequently entered into commercial operation in December 2020. Buy the profile here.
Description
The project was developed by Clearway Energy Group and is currently owned by Clearway Energy with a stake of 100%.
The project supplies enough clean energy to power 38,000 households.
Development status
The project is currently active. The project construction commenced in 2020 and subsequently entered into commercial operation in December 2020.
Power purchase agreement
The power generated from the project is sold to Avista under a power purchase agreement for a period of 20 years from 2020. The contracted capacity is 50MW.
Contractors involved
Blattner Energy was selected to render engineering procurement construction services for the wind power project.
Siemens Gamesa Renewable Energy was selected as the turbine supplier for the wind power project. The wind power project consists of 57 turbines.
For more details on Rattlesnake Flat Wind Farm, buy the profile here.
About Clearway Energy Group
Clearway Energy Group LLC (Clearway) is focused on providing customers with low-cost, clean power generated by solar and wind. Clearway is headquartered in the US.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.