R.W. Miller Steam Turbine Plant is a 366MW gas fired power project. It is located in Texas, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in October 1968. Buy the profile here.
Description
The project is currently owned by Brazos Electric Cooperative.
It is a Steam Turbine power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Distillate Fuel Oil. The fuel is procured from Embridge, Huckabay, Atmos, Enterprise.
The project generated 131,654MWh of electricity.
Development status
The project got commissioned in October 1968.
Contractors involved
R.W. Miller Steam Turbine Plant (R.W. Miller Steam Turbine Plant Unit I) is equipped with Siemens Energy Tandem Compound, Non-reheat steam turbine. The phase consists of 1 steam turbine with 66MW nameplate capacity.
R.W. Miller Steam Turbine Plant (R.W. Miller Steam Turbine Plant Unit II) is equipped with GE Power Tandem Compound, Reheat steam turbine. The phase consists of 1 steam turbine with 100MW nameplate capacity.
R.W. Miller Steam Turbine Plant (R.W. Miller Steam Turbine Plant Unit III) is equipped with Siemens Energy Tandem Compound, Reheat steam turbine. The phase consists of 1 steam turbine with 200MW nameplate capacity.
Siemens Energy supplied Hydrogen Cooled electric generator for the R.W. Miller Steam Turbine Plant (R.W. Miller Steam Turbine Plant Unit I).
GE Power supplied Hydrogen Cooled electric generator for the R.W. Miller Steam Turbine Plant (R.W. Miller Steam Turbine Plant Unit II).
Siemens Energy supplied Hydrogen Cooled electric generator for the R.W. Miller Steam Turbine Plant (R.W. Miller Steam Turbine Plant Unit III).
Amec Foster Wheeler supplied steam boiler for the R.W. Miller Steam Turbine Plant (R.W. Miller Steam Turbine Plant Unit I).
Riley Power supplied steam boiler for the R.W. Miller Steam Turbine Plant (R.W. Miller Steam Turbine Plant Unit II).
Riley Power supplied steam boiler for the R.W. Miller Steam Turbine Plant (R.W. Miller Steam Turbine Plant Unit III).
For more details on R.W. Miller Steam Turbine Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.