Qinbei Power Plant Phase I & II is a 2,400MW coal fired power project. It is located in Henan, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in November 2004. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Qinbei Power Plant Phase I & II

Buy the Profile

Data Insights

The gold standard of business intelligence.

Find out more

Description

Huaneng Power International, Henan Construction and Investment and Jiyuan Investment Group are currently owning the project having ownership stake of 60%, 35% and 5% respectively.

It is a Steam Turbine power plant that is used for Baseload. The fuel is procured from Shanxi Province.

Development status

The project got commissioned in November 2004.

Power purchase agreement

The power generated from the project is sold to State Grid Henan Electric Power under a power purchase agreement.

Contractors involved

Henan Construction and Investment was selected to render engineering procurement construction services for the coal fired power project.

Harbin Electric was selected as the turbine supplier for thermal power project. The project consists of 4 units of CLN600-24.2 / 566/566 turbines, each with 600MW nameplate capacity.

Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit I).

Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit I).

Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit I).

Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit II).

Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit II).

Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit II).

Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit III).

Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit III).

Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit III).

Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit IV).

Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit IV).

Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit IV).

MHPS Dongfang Boiler supplied steam boiler for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit I).

MHPS Dongfang Boiler supplied steam boiler for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit I).

MHPS Dongfang Boiler supplied steam boiler for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit I).

MHPS Dongfang Boiler supplied steam boiler for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit II).

MHPS Dongfang Boiler supplied steam boiler for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit II).

MHPS Dongfang Boiler supplied steam boiler for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit II).

MHPS Dongfang Boiler supplied steam boiler for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit III).

MHPS Dongfang Boiler supplied steam boiler for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit III).

MHPS Dongfang Boiler supplied steam boiler for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit III).

MHPS Dongfang Boiler supplied steam boiler for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit IV).

MHPS Dongfang Boiler supplied steam boiler for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit IV).

MHPS Dongfang Boiler supplied steam boiler for the Qinbei Power Plant Phase I & II (Qinbei Power Plant Phase I & II Unit IV).

For more details on Qinbei Power Plant Phase I & II, buy the profile here.

This content was updated on 14 October 2024

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.