Pesqueria Combined Cycle Power Plant is a 900MW gas fired power project. It is located in Nuevo Leon, Mexico. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in March 2017. Buy the profile here.
Description
The project is developed and owned by Techgen S.A. de. The company has a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Kinder-Morgan Transportation.
The project generated 6,387,000MWh of electricity.
Development status
The project got commissioned in March 2017.
Power purchase agreement
The power generated from the project is sold to Comision Federal de Electricidad under a power purchase agreement.
Contractors involved
Techint E&C was selected to render engineering procurement construction services for the gas fired power project.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 3 units of 7FA.05 gas turbines.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of D11 steam turbine.
GE Power supplied electric generator for the project.
GE Power is the O&M contractor for thermal power project.
For more details on Pesqueria Combined Cycle Power Plant, buy the profile here.