Pedro Camejo Power Plant is a 300MW gas fired power project. It is located in Carabobo, Venezuela. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in March 2006. Buy the profile here.
Description
The project is currently owned by Corporacion Electrica Nacional with a stake of 100%.
It is a Gas Turbine power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel.
The project generated 2,206,630MWh of electricity.
Development status
The project got commissioned in March 2006.
Contractors involved
Siemens was selected as the turbine supplier for the Gas fired project. The company provided 2 units of SGT6-5000F gas turbines, each with 150MW nameplate capacity.
Siemens supplied electric generator for the project.
For more details on Pedro Camejo Power Plant, buy the profile here.