Omotosho Power Plant Phase II is a 504.4MW gas fired power project. It is located in Ondo, Nigeria. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in July 2012. Buy the profile here.
Description
The project is currently owned by Omotosho Generation with a stake of 100%.
It is a Gas Turbine power plant.
Development status
The project got commissioned in July 2012.
Contractors involved
China Machinery Engineering was selected to render engineering procurement construction services for the gas fired power project.
GE Power was selected as the turbine supplier for thermal power project. The project consists of 4 units of 9E turbines, each with 126.1MW nameplate capacity.
GE Power supplied electric generator for the Omotosho Power Plant Phase II (Omotosho Power Plant Phase II Unit I).
GE Power supplied electric generator for the Omotosho Power Plant Phase II (Omotosho Power Plant Phase II Unit II).
GE Power supplied electric generator for the Omotosho Power Plant Phase II (Omotosho Power Plant Phase II Unit III).
GE Power supplied electric generator for the Omotosho Power Plant Phase II (Omotosho Power Plant Phase II Unit IV).
For more details on Omotosho Power Plant Phase II, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.