Okumino is a 1,554MW hydro power project. It is located on Itadorigawa river/basin in Gifu, Japan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. The project construction commenced in 1976 and subsequently entered into commercial operation in 1994. Buy the profile here.
Description
The project is currently owned by Chubu Electric Power.
Okumino is a pumped storage project. The hydro reservoir capacity is 17.2 million cubic meter. The net head of the project is 486m.
The project consists of 6 generators.
Development status
The project construction commenced in 1976 and subsequently entered into commercial operation in 1994.
Contractors involved
Toshiba Energy Systems and Solutions was selected as the turbine supplier for the hydro power project. The project consists of 6 units of Francis turbines, each with 259MW nameplate capacity.
For more details on Okumino, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.