Ocotillo Modernization Project is a 510MW gas fired power project. It is located in Arizona, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 2019. Buy the profile here.
Description
The project is developed and owned by Arizona Public Service.
It is a Gas Turbine power plant that is used for Peakload.
Development status
The project got commissioned in 2019.
Contractors involved
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 5 units of LMS100 gas turbines, each with 102MW nameplate capacity.
For more details on Ocotillo Modernization Project, buy the profile here.
About Arizona Public Service
Arizona Public Service Co (APS), a subsidiary of Pinnacle West Capital Corp, is an energy utility. It generates, procures, transmits, and distributes electricity to various regions. The company generates electricity using varied resources, namely, coal, nuclear, gas, oil, the solar, wind, geothermal, and biomass. Through demand response, day-ahead call option, exchange, tolling, purchase, and other agreements, APS procures electricity from third parties and owns interests in renewable energy projects, and transmission facilities that are in under development and construction phase. The company serves customers in Arizona. APS is headquartered in Phoenix, Arizona, the US.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.