Novo-Angren Cogeneration Plant is a 2,100MW coal fired power project. It is located in Tashkent, Uzbekistan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1985. Buy the profile here.
Description
The project is currently owned by JSC Uzbekenergo with a stake of 51%.
It is a Steam Turbine with Cogen power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is coal. In case of shortage of coal the plant can also run on Natural Gas.
Development status
The project got commissioned in 1985.
Contractors involved
Leningradsky Metallichesky Zavod was selected as the turbine supplier for the Coal fired project. The company provided 7 units of K-300-240-3 steam turbines, each with 300MW nameplate capacity.
Electrosila supplied TBB-320-2 electric generator for the project.
Electrosila supplied TBB-320-2 electric generator for the project.
Electrosila supplied TBB-320-2 electric generator for the project.
Podolsk Machine-Building Plant ZIO supplied steam boiler for the project.
Podolsk Machine-Building Plant ZIO supplied steam boiler for the project.
Podolsk Machine-Building Plant ZIO supplied steam boiler for the project.
For more details on Novo-Angren Cogeneration Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.