Nizhnevartovskaya Thermal Power Plant is a 1,600MW gas fired power project. It is located in Khanty–Mansi Autonomous Okrug, Russia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in January 1993. Buy the profile here.
Description
The project was developed by NVGRES Holding. Inter RAO UES and Rosneft are currently owning the project having ownership stake of 74.99% and 25.01% respectively.
It is a Steam Turbine with Cogen power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Fuel Oil.
The project generated 11,908,000MWh of electricity.
Development status
The project got commissioned in January 1993.
Contractors involved
EMK-Atommash and Kvartz Vostochnaya Sibir were selected to render engineering procurement construction services for the gas fired power project.
The Gas fired project have been supplied by Electrosila and Leningradsky Metallichesky Zavod.
Electrosila supplied electric generator for the Nizhnevartovskaya Thermal Power Plant (Nizhnevartovskaya Thermal Power Plant Unit I).
Electrosila supplied electric generator for the Nizhnevartovskaya Thermal Power Plant (Nizhnevartovskaya Thermal Power Plant Unit I).
Electrosila supplied electric generator for the Nizhnevartovskaya Thermal Power Plant (Nizhnevartovskaya Thermal Power Plant Unit II).
Electrosila supplied electric generator for the Nizhnevartovskaya Thermal Power Plant (Nizhnevartovskaya Thermal Power Plant Unit II).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Nizhnevartovskaya Thermal Power Plant (Nizhnevartovskaya Thermal Power Plant Unit I).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Nizhnevartovskaya Thermal Power Plant (Nizhnevartovskaya Thermal Power Plant Unit I).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Nizhnevartovskaya Thermal Power Plant (Nizhnevartovskaya Thermal Power Plant Unit II).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Nizhnevartovskaya Thermal Power Plant (Nizhnevartovskaya Thermal Power Plant Unit II).
For more details on Nizhnevartovskaya Thermal Power Plant, buy the profile here.