Newman Combined Cycle Power Plant is a 628MW gas fired power project. It is located in Texas, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in August 1975. Buy the profile here.
Description
The project is currently owned by El Paso Electric with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Kinder Morgan, ONEOK Westex Transmission LP.
Development status
The project got commissioned in August 1975.
Contractors involved
Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock I) is equipped with Siemens W501 gas turbines. The phase consists of 2 gas turbines with 85MW nameplate capacity.
Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock I) is equipped with Siemens Energy steam turbine. The phase consists of 1 steam turbine with 120MW nameplate capacity.
Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit I) is equipped with GE Power 7E.03 gas turbine. The phase consists of 1 gas turbine with 86.5MW nameplate capacity.
Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit II) is equipped with GE Power 7E.03 gas turbine. The phase consists of 1 gas turbine with 86.5MW nameplate capacity.
Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit III) is equipped with Fuji Electric steam turbine. The phase consists of 1 steam turbine with 165MW nameplate capacity.
GE Power supplied electric generator for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit I).
GE Power supplied electric generator for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit II).
Fuji Electric supplied electric generator for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit III).
Siemens Energy supplied steam boiler for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock I).
Nooter/Eriksen supplied steam boiler for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit III).
For more details on Newman Combined Cycle Power Plant, buy the profile here.
Data Insights
From