Munchen Sud Combined Cycle Power Plant is a 305MW gas fired power project. It is located in Bavaria, Germany. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1980. Buy the profile here.
Description
The project is currently owned by Stadtwerke Munchen with a stake of 100%.
It is a CCGT with Cogen power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Oil.
Development status
The project got commissioned in 1980.
Contractors involved
MAB Anlagenbau Germany, Siemens and VA Tech Wabag were selected to render engineering procurement construction services for the gas fired power project.
The Gas fired project have been supplied by GE Power and Siemens.
Siemens supplied electric generator for the project.
Siemens supplied electric generator for the project.
Siemens supplied electric generator for the project.
Siemens supplied steam boiler for the project.
Siemens supplied steam boiler for the project.
Siemens supplied steam boiler for the project.
For more details on Munchen Sud Combined Cycle Power Plant, buy the profile here.