Mosul Main Dam is a 750MW hydro power project. It is located on Tigris river/basin in Nineveh, Iraq. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1981 and subsequently entered into commercial operation in 1986. Buy the profile here.
Description
The project is currently owned by Government of Iraq.
The hydro reservoir capacity is 11,110 million cubic meter. The gross head of the project is 73.5m. The project generated 2,420 GWh of electricity.
Development status
The project construction commenced in 1981 and subsequently entered into commercial operation in 1986.
Contractors involved
Toshiba Energy Systems and Solutions was selected as the turbine supplier for the hydro power project. The company provided 4 units of francis turbines, each with 187.5MW nameplate capacity.
Toshiba Energy Systems and Solutions supplied electric generator(s) for the project.
For more details on Mosul Main Dam, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.