Mosenergo TEP-25 Power Plant is a 1,370MW gas fired power project. It is located in Moscow, Russia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in January 1975. Buy the profile here.
Description
The project is currently owned by Mosenergo with a stake of 100%.
It is a Steam Turbine with Cogen power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Fuel Oil.
The project generated 8,256,000MWh of electricity.
Development status
The project got commissioned in January 1975.
Contractors involved
Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit I) is equipped with Leningradsky Metallichesky Zavod PT-60-130 steam turbine. The phase consists of 1 steam turbine with 60MW nameplate capacity.
Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit II) is equipped with Leningradsky Metallichesky Zavod PT-60-130 steam turbine. The phase consists of 1 steam turbine with 60MW nameplate capacity.
Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit III) is equipped with Leningradsky Metallichesky Zavod T-250-240 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.
Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit IV) is equipped with Leningradsky Metallichesky Zavod T-250-240 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.
Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit V) is equipped with Leningradsky Metallichesky Zavod T-250-240 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.
Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit VI) is equipped with Leningradsky Metallichesky Zavod T-250-240 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.
Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit VII) is equipped with Leningradsky Metallichesky Zavod T-250-240 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.
Electrosila supplied electric generator for the project.
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit III).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit IV).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit V).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit VI).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit VII).
For more details on Mosenergo TEP-25 Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.