Kulekhani No 1 is a 60MW hydro power project. It is located on Kulekhani river/basin in Bagmati, Nepal. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1982. Buy the profile here.
Description
The project is currently owned by Nepal Electricity Authority with a stake of 100%.
Kulekhani No 1 is a reservoir based project. The hydro reservoir capacity is 85.3 million cubic meter. The net head of the project is 550m. The penstock length is 1,324m. The penstock diameter is 2.1m. The project generated 211 GWh of electricity.
Development status
The project got commissioned in 1982.
Contractors involved
Bharat Heavy Electricals was selected as the turbine supplier for the hydro power project. The company provided 2 units of pelton turbines, each with 30MW nameplate capacity.
Bharat Heavy Electricals supplied electric generator(s) for the project. The generator capacity is 35 MVA.
For more details on Kulekhani No 1, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.