Jack Fusco Energy Center is a 675.6MW gas fired power project. It is located in Texas, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in May 2003. Buy the profile here.
Description
The project is currently owned by Calpine with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Brazos Valley Energy, LLC.
The project generated 2,263,478MWh of electricity.
The Gas fired project consists of 1 steam turbine with 275.6MW nameplate capacity.
Development status
The project got commissioned in May 2003.
Power purchase agreement
The power generated from the project is sold to Calpine under a power purchase agreement.
Contractors involved
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 2 units of 7F.04 gas turbines, each with 200MW nameplate capacity.
GE Power supplied electric generator for the project.
GE Power supplied electric generator for the project.
NEM Energy supplied steam boiler for the project.
NEM Energy supplied steam boiler for the project.
For more details on Jack Fusco Energy Center, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.