Hengelo Biomass Power Plant is a 20MW biopower project. It is located in Overijssel, Netherlands. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 2008. Buy the profile here.
Description
The project is currently owned by Twence.
The project generates 168GWh electricity and supplies enough clean energy to power 44,000 households.
The process of combustion has been adopted in this project to release the stored energy from the feed. Wood waste which is a kind of wood by-product is used as a feedstock to power the project.
Development status
The project got commissioned in 2008.
Contractors involved
Standardkessel Power Systems Holding was selected to render engineering procurement construction services for the biopower project.
Franco Tosi Meccanica was selected as the steam turbine supplier for the project. The company provided 1 turbine with 28.5MW nameplate capacity.
Standardkessel Power Systems Holding supplied steam boiler for the project. The boiler installed at the site has a capacity of 80TPH. The temperature witnessed inside the boiler is around 462Degree Celsius. The steam is pressurized inside the boiler at 68bar.
For more details on Hengelo Biomass Power Plant, buy the profile here.