GPPC Pipavav Power Project is a 702.86MW gas fired power project. It is located in Gujarat, India. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in March 2013. Buy the profile here.
Description
The project is currently owned by GSPC Pipavav Power with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Gujarat State Petroleum Corporation Ltd..
Development status
The project got commissioned in March 2013.
Power purchase agreement
The power generated from the project is sold to Gujarat Urja Vikas Nigam under a power purchase agreement for a period of 20 years. The contracted capacity is 702MW.
Contractors involved
Bharat Heavy Electricals was selected to render engineering procurement construction services for the gas fired power project.
GPPC Pipavav Power Project (GPPC Pipavav Power Project Block I) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 129MW nameplate capacity.
GPPC Pipavav Power Project (GPPC Pipavav Power Project Block I) is equipped with Bharat Heavy Electricals MS9001FA gas turbine. The phase consists of 1 gas turbine with 222.43MW nameplate capacity.
GPPC Pipavav Power Project (GPPC Pipavav Power Project Block II) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 129MW nameplate capacity.
GPPC Pipavav Power Project (GPPC Pipavav Power Project Block II) is equipped with Bharat Heavy Electricals MS9001FA gas turbine. The phase consists of 1 gas turbine with 222.43MW nameplate capacity.
Bharat Heavy Electricals supplied electric generator for the GPPC Pipavav Power Project (GPPC Pipavav Power Project Block I).
Bharat Heavy Electricals supplied electric generator for the GPPC Pipavav Power Project (GPPC Pipavav Power Project Block II).
Bharat Heavy Electricals supplied steam boiler for the GPPC Pipavav Power Project (GPPC Pipavav Power Project Block I).
Bharat Heavy Electricals supplied steam boiler for the GPPC Pipavav Power Project (GPPC Pipavav Power Project Block II).
Sogex Oman is the O&M contractor for thermal power project. The operation and maintenance contract commenced from 2012, for a period of 10 years.
For more details on GPPC Pipavav Power Project, buy the profile here.