Filisur is a 65MW hydro power project. It is located on Glaris (Landwasser), Bergun (Albula) river/basin in Graubunden, Switzerland. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1961 and subsequently entered into commercial operation in 1966. Buy the profile here.
Description
Axpo Power, Elektrizitatswerk Davos and Kanton Graubunden are currently owning the project having ownership stake of 75%, 15% and 5% respectively.
Filisur is a run-of-river project. The hydro reservoir capacity is 0.09 million cubic meter. The project generated 286 GWh of electricity.
The hydro power project consists of 2 turbines, each with 32.5MW nameplate capacity.
Development status
The project construction commenced in 1961 and subsequently entered into commercial operation in 1966.
For more details on Filisur, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.