Dadri Combined Cycle Power Plant is an 829.78MW gas fired power project. It is located in Uttar Pradesh, India. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in May 1992. Buy the profile here.
Description
The project is developed and owned by NTPC. The company has a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Hazira Bijaipur Jagdispur Gas Pipeline.
Dadri Combined Cycle Power Plant (Dadri Combined Cycle Power Plant Block I Unit III) consists of 1 steam turbine with 154.51MW nameplate capacity.
Dadri Combined Cycle Power Plant (Dadri Combined Cycle Power Plant Block II Unit III) consists of 1 steam turbine with 154.51MW nameplate capacity.
Development status
The project got commissioned in May 1992.
Power purchase agreement
Dakshin Haryana Bijli Vitran Nigam and Uttar Haryana Bijli Vitran Nigam are the power offtakers from the project.
Contractors involved
Dadri Combined Cycle Power Plant (Dadri Combined Cycle Power Plant Block I Unit I) is equipped with Siemens SGT5-2000E gas turbine. The phase consists of 1 gas turbine with 130.19MW nameplate capacity.
Dadri Combined Cycle Power Plant (Dadri Combined Cycle Power Plant Block I Unit II) is equipped with Siemens SGT5-2000E gas turbine. The phase consists of 1 gas turbine with 130.19MW nameplate capacity.
Dadri Combined Cycle Power Plant (Dadri Combined Cycle Power Plant Block II Unit I) is equipped with Siemens SGT5-2000E gas turbine. The phase consists of 1 gas turbine with 130.19MW nameplate capacity.
Dadri Combined Cycle Power Plant (Dadri Combined Cycle Power Plant Block II Unit II) is equipped with Siemens SGT5-2000E gas turbine. The phase consists of 1 gas turbine with 130.19MW nameplate capacity.
Bharat Heavy Electricals supplied steam boiler for the Dadri Combined Cycle Power Plant (Dadri Combined Cycle Power Plant Block I Unit I).
Bharat Heavy Electricals supplied steam boiler for the Dadri Combined Cycle Power Plant (Dadri Combined Cycle Power Plant Block I Unit II).
Bharat Heavy Electricals supplied steam boiler for the Dadri Combined Cycle Power Plant (Dadri Combined Cycle Power Plant Block I Unit III).
Bharat Heavy Electricals supplied steam boiler for the Dadri Combined Cycle Power Plant (Dadri Combined Cycle Power Plant Block II Unit I).
Bharat Heavy Electricals supplied steam boiler for the Dadri Combined Cycle Power Plant (Dadri Combined Cycle Power Plant Block II Unit II).
Bharat Heavy Electricals supplied steam boiler for the Dadri Combined Cycle Power Plant (Dadri Combined Cycle Power Plant Block II Unit III).
NTPC was contracted to render operations & maintenance services for the project.
For more details on Dadri Combined Cycle Power Plant, buy the profile here.
About NTPC
NTPC Ltd (NTPC) is an energy company. It has presence in the entire value chain of the power generation business. The company produces electricity and sells it to state power utilities on wholesale basis. NTPC generates electricity using coal, gas, liquid fuel, hydro and other renewable sources. It also provides consultancy, e-mobility solutions, project management and supervision; holds interests in coal mining blocks; and carries out energy trading, oil and gas exploration, training of power professionals, rural electrification, ash utilization and coal mining. NTPC is headquartered in New Delhi, India.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.