Crookwell III is a 57.6MW onshore wind power project. It is planned in New South Wales, Australia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in a single phase. Post completion of the construction, the project is expected to get commissioned in 2024. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Crookwell III

Buy the Profile

Data Insights

The gold standard of business intelligence.

Find out more

Description

The project is being developed and currently owned by Crookwell Development. The company has a stake of 100%.

The project is expected to supply enough clean energy to power 40,000 households, to offset 181,436.948t of carbon dioxide emissions (CO2) a year.

The project will have 95m high towers.

Development status

Post completion of the construction, the project is expected to get commissioned in 2024.

Power purchase agreement

The power generated from the project will be sold to Telstra Group under a power purchase agreement. The offtake capacity is expected to be 46.08MW.

Contractors involved

Vestas Wind Systems will be the turbine supplier for the wind power project. The company is expected to provide 16 units of V126-3.45MW turbines, each with 3.6MW nameplate capacity.

Vestas Wind Systems is expected to perform operations and maintenance for the wind power project for a period of 15 years.

For more details on Crookwell III, buy the profile here.

This content was updated on 14 October 2024

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.