Claus Power Plant C is a 1,300MW gas fired power project. It is located in Limburg, Netherlands. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in June 2012. Buy the profile here.
Description
The project is currently owned by RWE Generation with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant.
Development status
The project got commissioned in June 2012.
Contractors involved
GE Power was selected to render engineering procurement construction services for the gas fired power project.
The Gas fired project have been supplied by GE Power and Siemens.
GE Power supplied TOPAIR electric generator for the project.
GE Power supplied TOPAIR electric generator for the project.
GE Power supplied steam boiler for the project.
GE Power supplied steam boiler for the project.
GE Power is the O&M contractor for thermal power project for a period of 12 years.
For more details on Claus Power Plant C, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.