Citrus County Combined Cycle Power Plant is a 1,970.6MW gas fired power project. It is located in Florida, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in October 2018. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Citrus County Combined Cycle Power Plant

Buy the Profile

Data Insights

The gold standard of business intelligence.

Find out more

Description

The project is currently owned by Duke Energy Florida with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Ultra-Low Sulfur Diesel. The fuel is procured from Sabal Trail Pipeline.

The project generated 1,370,323MWh of electricity.

Development status

The project got commissioned in October 2018.

Contractors involved

Fluor was selected to render engineering procurement construction services for the gas fired power project.

Citrus County Combined Cycle Power Plant (Citrus County Combined Cycle Power Plant Unit I) is equipped with Mitsubishi Power steam turbine. The phase consists of 1 steam turbine with 364.7MW nameplate capacity.

Citrus County Combined Cycle Power Plant (Citrus County Combined Cycle Power Plant Unit I) is equipped with Mitsubishi Power M501GAC gas turbines. The phase consists of 2 gas turbines with 310.3MW nameplate capacity.

Citrus County Combined Cycle Power Plant (Citrus County Combined Cycle Power Plant Unit II) is equipped with Mitsubishi Power steam turbine. The phase consists of 1 steam turbine with 364.7MW nameplate capacity.

Citrus County Combined Cycle Power Plant (Citrus County Combined Cycle Power Plant Unit II) is equipped with Mitsubishi Power M501GAC gas turbines. The phase consists of 2 gas turbines with 310.3MW nameplate capacity.

Mitsubishi Power supplied electric generator for the Citrus County Combined Cycle Power Plant (Citrus County Combined Cycle Power Plant Unit I).

Mitsubishi Power supplied electric generator for the Citrus County Combined Cycle Power Plant (Citrus County Combined Cycle Power Plant Unit II).

Vogt Power International supplied steam boiler for the project.

For more details on Citrus County Combined Cycle Power Plant, buy the profile here.

This content was updated on 14 October 2024

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.