Camden Power Station is a 1,561MW coal fired power project. It is located in Mpumalanga, South Africa. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in March 2005. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Camden Power Station

Buy the Profile

Data Insights

The gold standard of business intelligence.

Find out more

Description

The project is currently owned by Eskom Holdings SOC with a stake of 100%.

It is a Steam Turbine power plant. The fuel is procured from Usutu South, West and East Mines - Trans-Natal Coal Mining Company.

Development status

The project got commissioned in March 2005.

Contractors involved

Camden Power Station (Camden Power Station Unit I) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 200MW nameplate capacity.

Camden Power Station (Camden Power Station Unit II) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 200MW nameplate capacity.

Camden Power Station (Camden Power Station Unit III) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 200MW nameplate capacity.

Camden Power Station (Camden Power Station Unit IV) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 196MW nameplate capacity.

Camden Power Station (Camden Power Station Unit V) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 195MW nameplate capacity.

Camden Power Station (Camden Power Station Unit VI) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 195MW nameplate capacity.

Camden Power Station (Camden Power Station Unit VII) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 190MW nameplate capacity.

Camden Power Station (Camden Power Station Unit VIII) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 185MW nameplate capacity.

Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit I).

Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit II).

Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit III).

Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit IV).

Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit V).

Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit VI).

Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit VII).

Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit VIII).

Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit I). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.

Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit II). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.

Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit III). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.

Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit IV). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.

Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit V). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.

Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit VI). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.

Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit VII). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.

Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit VIII). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.

For more details on Camden Power Station, buy the profile here.

This content was updated on 14 October 2024

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.