Bleiloch is an 80MW hydro power project. It is located on Saale river/basin in Thuringia, Germany. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1930 and subsequently entered into commercial operation in 1932. Buy the profile here.
Description
The project is currently owned by Vattenfall with a stake of 100%.
Bleiloch is a pumped storage project. The hydro reservoir capacity is 215 million cubic meter.
Development status
The project construction commenced in 1930 and subsequently entered into commercial operation in 1932.
Contractors involved
Voith Hydro Holding was selected as the turbine supplier for the hydro power project. The company provided 2 units of francis turbines, each with 40MW nameplate capacity.
Brown Boveri & Cie supplied 2 electric generators for the project.
For more details on Bleiloch, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.