Bihai is a 61.2MW hydro power project. It is located on Hoping river/basin in Hualien County, Taiwan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1995 and subsequently entered into commercial operation in 2011. Buy the profile here.
Description
The project is currently owned by Taiwan Power.
Bihai is a reservoir based project. The hydro reservoir capacity is 0.64 million cubic meter. The net head of the project is 416.8m. The project generated 237 GWh of electricity.
Development status
The project construction commenced in 1995 and subsequently entered into commercial operation in 2011.
Contractors involved
Bharat Heavy Electricals was selected as the turbine supplier for the hydro power project. The company provided 1 unit of pelton turbine with 62.5MW nameplate capacity.
Bharat Heavy Electricals supplied 1 electric generator for the project. The generator capacity is 68 MVA.
For more details on Bihai, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.